L&T Creates History in Nuclear Construction
L&T creates history in nuclear construction
Taking a giant leap towards modularisation in construction methodologies, L&T’s Heavy Civil Infrastructure team at Kakrapar Atomic Power Plant lifted and installed a 355 MT Inner Containment dome liner as a single unit. The team had worked tirelessly over a four-month period to create the structure. This involved executing over 53 km of welding to piece the structure together to form a unique tori-spherical shape, brought about by the two-dimensional bending of the backing members.
The Atomic Energy Regulatory Board (AERB), one of the toughest regulatory bodies in the country, complimented them saying that they were unable to differentiate between the 3D model of the dome liner and the one created by L&T.
The flawless execution of the project came on the heels of five consecutive RoSPA Gold Medals and three consecutive Sarvasreshta Suraksha Puraskar from National Safety Council of India, for their impeccable safety record.
Kakrapar Atomic Power Plant construction
   
PREVIOUS
|
NEXT
Awards   |   Assurance Statement   |   Locations   |   Communication on Progress   |   Feedback
Privacy Policy          Copyright © 2017 L&T
DOWNLOAD
REPORT
Improving Attendance
Through Attention
   
Water Positive
Campuses
   
L&T Creates History
in Nuclear Construction
   
Cream of
The Crop
   
Safer Project Execution
Also Reduces Costs
Safety First
   
Soil for Water –
A Winner All Round
   
Re-powering
Fallow Lands
   
Digitally Driven
Schooling
   
Keeping an Eye on
Mumbai - The L&T Way
Improving Attendance Through Attention
   
Water Positive Campuses
   
L&T Creates History in Nuclear Construction
   
Cream of The Crop
   
Safer Project Execution Also Reduces Costs
Safety First
   
Soil for Water –
A Winner All Round
   
Re-powering Fallow Lands
   
Digitally Driven Schooling
   
Keeping an Eye on
Mumbai - The L&T Way
Top